Default Wet weather and concrete

How wet is too wet to pour concrete? For what seems like six months now it rains every 5 days or so and the ground isn't really drying out. If it doesn't rain for three weeks or two weeks think I'll be able to pour?
__________________
Tim
Self appointed director of junk, and old vehicles.
Reply With Quote
  #2  
Old 03-11-2019, 05:21 PM
milomilo's Avatar
milomilo milomilo is offline
Auction Addict
 
Join Date: May 2010
Location: Wheatland, Wyoming
Posts: 15,058
Default

It is only rain after the concrete is in place, then you have to cover it for 2-3 days or until the rain stops. Humidity is a good thing for concrete. Slows down the evaporation so the concrete will be stronger. Visible ground water should be gone before you place the concrete.
__________________
Chris

Politics is the art of looking for trouble, finding it everywhere, diagnosing it incorrectly and applying the wrong remedies.
Groucho Marx
Reply With Quote
  #3  
Old 03-11-2019, 05:46 PM
slip knot slip knot is offline
Senior Member
 
Join Date: Jul 2015
Location: Texas gulf coast
Posts: 396
Default

Around here they will pour as long as theres no standing water in the forms and the trucks don't get stuck onsite. its been so wet around here that the concrete pumpers are even being used for home foundations. That was unheard of until now.
Reply With Quote
  #4  
Old 03-11-2019, 07:10 PM
greywynd's Avatar
greywynd greywynd is offline
I can dig it
 
Join Date: Dec 2005
Location: Wainwright, Alberta
Posts: 4,740
Default

Quote:
Originally Posted by slip knot View Post
Around here they will pour as long as theres no standing water in the forms and the trucks don't get stuck onsite. its been so wet around here that the concrete pumpers are even being used for home foundations. That was unheard of until now.


Where I was in Onterrible that was common practice. Many of the bigger form companies have their own pumpers, and the subdivisions are so tight that pumping concrete is just how it’s done.

Form footings, pump in the concrete. Form basement walls, pump concrete. Once the forms are stripped, usually a stone slinger is used to place clear stone around the footing weeping tile, and under the basement floor. Often the concrete companies own the slingers as well. On bigger developments I’ve seen the slingers and concrete pumpers stay on site all day, day after day.

Even basement floors will get the pumpers brought in, and the hose put in through window and stairway openings to minimize labour.


Sent from my iPhone using ShopFloorTalk mobile app
Reply With Quote
  #5  
Old 03-11-2019, 07:26 PM
Ironman's Avatar
Ironman Ironman is offline
Iron Modification Investigator
 
Join Date: Feb 2008
Location: Warburg, Alberta, Canada
Posts: 13,716
Default

Tim, concrete hardens under water as well. When you mix water and cement yopu have an initial setting time, when it is fluid. Then it starts the process of hardening. The hardening process is a crystal growth off of a particle of aggregate. If you can look under a microscope at concrete that has started to set and someone threw in a bit of water and mixed it up again, you would see thousands of broken off crystals of calcium carbonate. That is why they say do not remix conc, as there is limited material in the mix to grow crystals, and this requires water to do so.
In three months 90% of the hardening is completed and the final hardening is complete by the thirteenth year.

Just don't get the truck stuck before it has unloaded.
__________________
Gerry
You got freedom of speech, if you don't say too much.
Aaron Neville.

The virtue is always a cover for the sin. That's the key to understanding the modern left. Whatever they're accusing you of doing, they are doing themselves but more enthusiastically. And that's definitely the story of Justin Trudeau. Tucker Carlson
Reply With Quote
  #6  
Old 03-11-2019, 08:14 PM
OldRedFord's Avatar
OldRedFord OldRedFord is offline
Kibble King
 
Join Date: Mar 2005
Location: Hull GA
Posts: 3,580
Send a message via AIM to OldRedFord Send a message via Yahoo to OldRedFord
Default

Interesting. I thought pouring over mushy muddy clay would be bad.
__________________
Tim
Self appointed director of junk, and old vehicles.
Reply With Quote
  #7  
Old 03-11-2019, 09:42 PM
slip knot slip knot is offline
Senior Member
 
Join Date: Jul 2015
Location: Texas gulf coast
Posts: 396
Default

Quote:
Originally Posted by greywynd View Post
Where I was in Onterrible that was common practice. Many of the bigger form companies have their own pumpers, and the subdivisions are so tight that pumping concrete is just how it’s done.

Form footings, pump in the concrete. Form basement walls, pump concrete. Once the forms are stripped, usually a stone slinger is used to place clear stone around the footing weeping tile, and under the basement floor. Often the concrete companies own the slingers as well. On bigger developments I’ve seen the slingers and concrete pumpers stay on site all day, day after day.

Even basement floors will get the pumpers brought in, and the hose put in through window and stairway openings to minimize labour.


Sent from my iPhone using ShopFloorTalk mobile app
Here everything is slab on grade with maybe 2ft deep footing. No frost line here
The illegals and chutes are cheaper than pumpers but pumpers are cheaper than heavy recovery bills. Nobody wants a stuck concrete truck.
Reply With Quote
  #8  
Old 03-11-2019, 09:48 PM
LKeithR's Avatar
LKeithR LKeithR is offline
Hey...wait...is there a prize?
 
Join Date: Aug 2011
Location: Langley, B.C.
Posts: 5,053
Default

Quote:
Originally Posted by greywynd View Post
...Where I was in Onterrible that was common practice. Many of the bigger form companies have their own pumpers, and the subdivisions are so tight that pumping concrete is just how it’s done...
Yeah, nobody hand bombs concrete around here--it's all been pumped for years. I can't remember the last time I saw a construction site that didn't pump the concrete...
__________________
Keith

Measure twice and cut once...or...wait, was that the other way around?
Reply With Quote
  #9  
Old 03-11-2019, 11:50 PM
arizonian's Avatar
arizonian arizonian is offline
Elite Member
 
Join Date: Jul 2007
Location: Tucson, Arizona
Posts: 1,255
Default

I gotta throw this out there...

Concrete will set under water, but what is bearing it's weight? If it's mud (soil, clay, etc.), and the mud dries out, what prevents the mud from shrinking and the slab settling off kilter?

I may be way off base, I am not a concrete guy, but I would not pour any concrete over really wet mud. As has been mentioned, no standing water. I would also dig down if necessary and backfill with what I call AB (aggregate base) and compact.

Check with some local builders, see what they do. Maybe write an email to Scott Wadsworth (Essential Craftsman) asking his opinion. EC has mentioned that he does not want to wait until right before the rainy season starts to get moving on the house he is building.

Go back and read this post from member DDA52, send him a PM, see what he would do.

Do your due diligence to make sure YOUR project comes out as you want it.
__________________
Bill in sunny Tucson

I believe in gun control.

Gun Control: The ability to consistently hit what you are aiming at.

Weldor by choice, engineer by necessity.

Last edited by arizonian; 03-12-2019 at 12:09 AM.
Reply With Quote
  #10  
Old 03-11-2019, 09:36 PM
toprecycler's Avatar
toprecycler toprecycler is offline
Elite Member
 
Join Date: Jan 2009
Location: Petoskey, Michigan
Posts: 3,902
Default

The concrete will harden up, but if it is too wet, you might not be able to finish the surface like you want. If you want it smooth, your concrete finishers might want it a little more dry. But if it is always raining, you might need to just get the footings done, and get the building put up and do the floor after you get the roof up to keep the rain off long enough for finishing.


Sent from my iPhone using ShopFloorTalk
__________________
Brian

You don't know what you don't know.

"It's what you learn after you know it all that counts." John Wooden
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On