#51
|
||||
|
||||
Quote:
run. 100A to the barn from the shop. My shop has it own 400 amp service and meter. I ran copper wire in PVC conduit. I liked the ideal of conduit for a little extra protection and I had some tree roots that could pose an issue. My electrician also recommend putting in larger than needed conduit in case I ever wanted to up service to 200 amp. Back in 96 it was all to codes.
__________________
Shade "Prepare to defend yourselves." -- Sergeant Major Basil L. Plumley, Ia Drang Valley |
#52
|
||||
|
||||
I went with 2.5 inch conduit. I was told 2" but wanted it a little easier to pull through and its the largest my meter base will take. I still need to buy a couple sticks(estimated), but I think I'll get them once I get the garage run finished.
|
#53
|
||||
|
||||
I'm late to the party. But happy with my Square D QO main panels and 400 amp service.
__________________
Tim Self appointed director of junk, and old vehicles. |
#54
|
|||
|
|||
SQ D QO, & QOB (bolt-on) breakers have been around a long time and will continue to be supported, which is my biggest fear about Leviton that they won't be, like T&B panels & their UL classified breakers, SQ D Trillaint, the T&B, breakers were UL classified to be used in most competitive makes of panels, then they disappeared.
|
#55
|
||||
|
||||
Busy day today. Started trenching to put conduit in.
Last edited by GWIZ; 04-26-2024 at 11:10 PM. Reason: Rotate picture |
#56
|
||||
|
||||
So I have the conduit from the pole to the garage in the ground and bolted to the pole. I need to mount the meter box the the garage, but the outside siding is that brittle asbestos tile/ hardy board. I'm probably going to put a bunch of 2x4s and 2x6s on the inside of the garage and just drill pilot holes to mount everything with. I'll keep it wet to make sure I don't stir up any dust. Then I'll mount my panel on the inside. AM I aloud to have the panel back to back with the meter box? Yes I will be asking the inspector but I figured I'd see what y'all have to say first. ITS COMING TOGETHER!
|
#57
|
|||
|
|||
I dont believe you can mount the meter can and breaker box back to back. I'm working on replacing my meter loop and the electric co-ops design criteria plainly states the meter can and the disconnect cant be back to back.
|
#58
|
||||
|
||||
They are not directly back to back, whatever the depth of the stud is. The inspector that was out today said he didn't care if I went out the back of the meter and into the panel so it may be a county thing. I need to look it over and see what will be easier in my opinion.
|
#59
|
||||
|
||||
This project has really kicked my ass!
So I currently have power to the new meter and panel in the garage. I have power to the house removed so I can put in the new meter box and panel. Duke took forever to come out and disconnect the house but they did it today. I'm running on a 30a circuit ran from the garage. Hope to have my inspection Monday and power restored Tuesday. What a shit show! Some random pics... Last edited by GWIZ; 05-10-2024 at 10:44 PM. Reason: Rotate picture |
#60
|
||||
|
||||
Well I've got power to the garage and the house! The final inspection is complete for the garage, I still need to hook up a couple things for the house.
|